Can Roofers Work in the Rain? What Happens to a New Jersey Roof Job When It Rains

By R&E Roofing11 min read
Two workers on a lift removing old roofing and damaged trim from a brick building, with a blue tarp covering the open part of the roof
A blue tarp kept over the open part of a roof while old roofing comes off. Illustrative photo, not an R&E Roofing job. Photo: Dennis Sylvester Hurd, Flickr, CC0.

The Short Answer

  • Shingles do not go on in the rain. GAF's Timberline instructions say roof decks and existing surfacing material must be dry before shingles are installed. IKO recommends stopping the installation and covering the roof when it starts to rain.
  • New Jersey's code points to those instructions. Section R905.1 of the state's one- and two-family dwelling subcode requires roof coverings to be applied in line with the manufacturer's installation instructions.
  • What a crew does in rain is protect the roof. That means a tarp over any open section, laid so water runs from top to bottom, and a temporary cover over a leak until a dry day.
  • Rain interrupts a job; it does not close a season. Newark Liberty International Airport averages 123.1 days a year with at least 0.01 inch of precipitation (NOAA 1991-2020 normals). November averages 8.8 such days, fewer than every other month except September's 8.7.

Why Shingles Wait for a Dry Roof

The question matters most during a roof replacement, when the old shingles are off and the wood deck is showing. The shingle makers answer it in their installation instructions, and the ones we read all point the same way.

  • The deck has to be dry. GAF's Timberline instructions: "Roof decks and existing surfacing material must be dry prior to installation of shingles."
  • Rain and dew both count. GAF's Pro Field Guide for steep-slope roofs warns that "decks subjected to rain or dew just before roofing may be filled with moisture" and that wood stored outdoors absorbs moisture.
  • A wet deck moves as it dries. GAF's Deck-Armor instructions say the deck must be dry "to help prevent buckling of the deck, which can result in deck movement and damage the primary roof covering." IKO says a wet wooden deck "can twist and deform the roof structure when it dries, causing shingles to buckle."
  • The shingles have to be dry too. IKO says to make sure shingles are dry before installing them so they stick to the roof right away, and to let wet shingles dry first. Bundles still in their packaging do not need protection from rain.
  • A wet roof is a slippery roof. IKO notes that a roof becomes slippery in a rain shower, which is dangerous for the roofer, and GAF's Deck-Armor instructions say wet conditions may make that underlayment's surface slippery.

New Jersey's code adds weight to those instructions. Section R905.1 of the state's one- and two-family dwelling subcode reads: "Roof coverings shall be applied in accordance with the applicable provisions of this section and the manufacturer's installation instructions." A crew that shingles over a wet deck is working against the instructions the code tells it to follow.

Sources, read November 23, 2026: GAF Timberline installation instructions, GAF Pro Field Guide, GAF Deck-Armor instructions, IKO, New Jersey one- and two-family dwelling subcode, R905.1 (UpCodes).

When Rain Arrives in the Middle of a Re-Roof

IKO notes that renovating a large roof can take up to several days, so the plan for rain matters more than any single forecast. IKO describes these steps:

  1. Open only what can be covered. "It is a good idea to open only a small part or one side of the roof, so it can be easily protected against the rain."
  2. Cover bare wood fast. When the old roofing is off and the wood deck is exposed, IKO says to finish that part of the job as soon as possible and cover the deck with underlayment.
  3. Tarp what is still open. When rain starts, IKO recommends stopping and covering the roof. Tarps "must be laid in such a way that the water runs down from the top to the bottom without the risk of infiltrating the uncovered roof," held down with weights such as shingle bundles, or with battens fixed along the lower edges of the roof and loaded with bundles.
  4. Cover the underlayment overnight. One of IKO's tips is to cover the underlayment with a tarp when the crew leaves the job, so shingles can go onto a dry underlayment the next morning.
Three people with long-handled roofing shovels stripping old asphalt shingles off a sloped roof, exposing the black felt underlayment and patches of wood decking beside a metal vent pipe
Old shingles coming off down to the felt, with patches of wood deck showing: the stage of a re-roof that most needs a cover if rain comes. Illustrative photo, not an R&E Roofing job. Photo: Kelly E. Barnes, U.S. Navy, public domain.

Underlayment is not always a rain cover

The makers do not agree on how far an underlayment can be trusted on its own, because it depends on the product:

  • IKO says a roof side covered with its underlayment "no longer needs protection against the rain," and asks that the underlayment not be left uncovered for more than 3 weeks.
  • GAF says its Deck-Armor underlayment is water resistant but "NOT WATERPROOF" and must not be used "as a temporary roof to protect property or possessions." Shingles must go over it within 180 days.
  • GAF says its leak barrier membranes are "not designed to be exposed for long periods of time" and are not to be left exposed longer than the product's limit, which GAF gives as 60 or 90 days.

So "the underlayment is on" can mean very different things during a wet week. Ask which product is going on your roof and whether the open sections will also be tarped. Our roof underlayment guide for New Jersey compares the types, and the roof replacement timeline walks through the stages of the job.

Sources, read November 23, 2026: IKO, GAF Deck-Armor instructions, GAF Pro Field Guide.

After the Rain: What Is Checked Before Work Restarts

None of the instructions we read sets a number of hours to wait after rain. They set a condition instead: dry.

  • Wet deck: IKO says to take the tarp off as soon as the rain stops and let wet parts of the wooden deck dry for a while before the underlayment goes on.
  • Wet underlayment: IKO recommends waiting for moisture on top of the underlayment to evaporate. "Trapped moisture can cause some hidden defects on the material such as buckling or wrinkling and can also lift the shingles." If the underlayment was tarped during the rain, IKO says shingles can go on right after it.
  • Wet shingles: IKO says to let them dry before installing them.
  • Morning dew counts: GAF names dew alongside rain as a way a deck fills with moisture just before roofing.

If part of your deck was rained on before it was covered, ask the crew to show you that section before underlayment goes over it. Our roof decking and sheathing guide explains what the deck is made of.

Sources, read November 23, 2026: IKO, GAF Pro Field Guide.

How Often It Rains in Newark, Month by Month

We use NOAA's 1991-2020 normals for Newark Liberty International Airport (station USW00014734). They show 46.60 inches of precipitation a year, 123.1 days with at least 0.01 inch and 76.3 days with at least 0.10 inch.

Newark Liberty International Airport, NOAA 1991-2020 normals: average precipitation and average number of days reaching each amount. Swipe the table sideways to see every column.
MonthPrecipitation (inches)Days with 0.01 in or moreDays with 0.10 in or moreDays with 0.50 in or more
January3.4210.66.22.5
February2.9810.05.72.3
March4.1310.96.92.7
April3.8711.56.32.4
May3.9711.47.32.7
June4.3410.97.13.0
July4.6610.06.73.2
August4.159.86.52.9
September3.828.75.72.6
October3.799.45.52.5
November3.338.85.32.4
December4.1411.17.13.3

What the table means for a roof job here:

  • There is no dry season. Every month averages between 8.7 and 11.5 days with measurable precipitation, so a rain day is part of planning in any month of the year.
  • Fall has the fewest wet days. September averages 8.7 and November 8.8, so a typical November has about 21 of its 30 days without measurable precipitation.
  • Spring and December have the most. April averages 11.5 days, May 11.4 and December 11.1.
  • Heavy days are fewer. Days with half an inch or more average 2.3 to 3.3 a month.

Cold brings its own rules for sealing shingles, which our winter roof repair guide for Essex County covers, and our best time to replace a roof in New Jersey guide compares the seasons.

Reading the chance of rain

The National Weather Service asks whether a 40 percent chance means rain 40 percent of the time, or over 40 percent of the area. Its answer: the probability of precipitation simply describes the probability that the forecast point gets at least 0.01 inch. A 40 percent chance is a 40 percent chance of measurable rain at that spot.

Sources, read November 23, 2026: NOAA NCEI monthly normals, NOAA NCEI annual normals, National Weather Service, the meaning of PoP.

A Leak During a Storm: What Can Be Done in the Rain

A leak cannot wait for a dry forecast. The lasting repair is still roofing work, and the makers' dry-surface rules apply to it, so a leak during rain is handled in two steps:

  1. Stop the water now. A tarp or other temporary cover over the damaged area, laid so water runs off it from top to bottom.
  2. Repair it on a dry day. New shingles go on once the deck and the shingles are dry, as the makers' instructions require.

R&E Roofing takes emergency calls on nights and weekends. See our emergency roof tarp page, the emergency roof repair page and our guide to a roof leak in heavy rain. For the repair itself, see roof repair in Essex County.

A truck-mounted conveyor boom raised to the roof of a single-story house, with a worker standing on the roof at its end
A conveyor raised to a roof to carry shingles up before they are installed. IKO says bundles still in their packaging do not need protection from rain, but the shingles must be dry when they go on. Illustrative photo, not an R&E Roofing job and not in Essex County. Photo: Alan Levine, Flickr, CC0.

Questions to Ask Before Your Roof Is Opened

The time to talk about rain is before the first shingle comes off. Questions worth asking your roofer:

  • How much of the roof will be open at one time?
  • Which underlayment is going on, and what does its maker say about leaving it exposed to rain?
  • Will the open sections be tarped at the end of each day, and who checks the tarps if rain comes at night?
  • If part of the deck gets wet before it is covered, will you show it to me before it is covered up?
  • If the forecast turns, how is the new start date set, and is anything in the price tied to the date?
  • Whose insurance answers for water that gets inside during the job?

For what the whole job costs here, see our roof replacement cost guide for Essex County and our roof replacement page.

Roof Replacement in the Towns Around Orange

R&E Roofing's office is at 573 Valley St in Orange. Our roof replacement pages for the nearby towns:

Questions Homeowners Ask About Roofing in the Rain

Can roofers work in the rain?

Not on the parts of a re-roof that need a dry surface. GAF's Timberline instructions say roof decks and existing surfacing material must be dry before shingles go on, and IKO recommends stopping the installation and covering the roof when it starts to rain. What a crew can do in rain is protect the roof: cover an open section with a tarp so water runs off it, and keep a leak covered until a dry day.

Can you shingle a roof in the rain?

Not by the makers' instructions. GAF requires a dry deck before shingles are installed, and IKO says to make sure the shingles themselves are dry and to let wet shingles dry before installing them. New Jersey's residential code section R905.1 requires roof coverings to be applied in line with the manufacturer's installation instructions.

What happens if it rains during a roof replacement?

The crew stops and covers what is open. IKO's advice is to open only a small part or one side of the roof at a time, to cover exposed wood decking with underlayment as soon as possible, and to tarp any part that is still open so water runs from the top to the bottom. When the rain stops, the tarp comes off and wet decking is left to dry before work continues.

Can you put shingles on wet underlayment?

The makers say to wait. IKO recommends waiting for the moisture on top of a wet underlayment to evaporate, because trapped moisture can cause buckling or wrinkling and lift the shingles. If the underlayment was tarped during the rain, IKO says work can continue right after it. GAF's instructions require the deck to be dry before shingles are installed.

Is underlayment enough to keep rain out overnight?

It depends on the product. IKO says a roof side covered with its underlayment no longer needs protection against the rain. GAF says its Deck-Armor underlayment is water resistant but not waterproof, and must not be used as a temporary roof to protect property or possessions. Ask your roofer which underlayment is going on and whether the open roof will also be tarped.

How long does a roof deck need to dry after rain?

None of the instructions we read gives a number of hours. GAF says the deck must be dry and that decks subjected to rain or dew just before roofing may be filled with moisture. IKO says to let wet parts of the deck dry for a while after the tarp comes off. The test is whether the deck is dry, not how many hours have passed.

Does a 40 percent chance of rain mean the job is off?

Not by itself. The National Weather Service defines the chance of rain as the probability that the forecast point gets at least 0.01 inch, so a 40 percent chance means a 40 percent chance of measurable rain at that spot. Whether to open a roof that day is a judgment about how much roof is open at once and how quickly it can be covered.

Sources

All read November 23, 2026.

Planning a Roof Replacement in Essex County?

R&E Roofing's office is at 573 Valley St, Orange, NJ 07050. Tell us your town and what is going on with your roof. You get a written estimate, and you can ask us every question on the list above before work is scheduled.

Office hours are Monday to Friday, 9 to 5, and we take emergency calls on nights and weekends.

Call (667) 204-1609

Ask for a roof replacement estimate in Essex County

Choose Roof Replacement under What do you need, or Emergency Roof Repair if water is coming in now. Add your town and what you see on the roof.

By sending this you agree to be contacted about your roof. R&E Roofing, Orange, NJ. Office hours Monday to Friday, 9 to 5.

Call (667) 204-1609Request an estimate